7.00.00 ELECTRIC POWER SUPPLY
7.01.00 The requirements of Electric Power Supply system are
specified herein on system basis. The contractor shall
be fully responsible for engineering and furnishing a
complete and operational system fully meeting the intent
and requirements of this specification and owner
approved drawings. All equipment and accessories
requires for completeness of this system shall be
furnished by the contractor whether these are
specifically mentioned herein or not. All the
equipments and sub-systems offered shall be from reputed
experienced manufacturer. All system cabinets,
enclosures & distribution boards shall be manufactured,
assembled, wired and fully tested as a complete assembly
as per the requirements of this specification at the
manufacturer’s works.
7.02.00 The power supply system shall be designed to meet the
electric power requirements of various C&I systems
including DDCMIS and shall be configured as described
below:-
a) For MMIPIS portion of DDCMIS including peripherals
like CRT’s. printers, disks etc.and other systems such
as SWAS, panel instruments, requiring stabilized AC
power, the bidder shall furnish a redundant UPS
system.
b) The power supply to each DDCMIS system cabinets is fed
through dual 240 V AC Feeder from UPS.
7.03.00 The UPS system in the above mentioned configurations
employed float cum boost chargers, battery banks, static
inverters, static switches. AC/DC distribution boards etc.
shall meet the following specification requirements as a
minimum.
7.04.00 Uninterruptible Power Supply(UPS) System
The UPS system shall have 2×100% parallel redundant
chargers and inverters, 2×100% battery bank, bypass line
transformers and voltage stabilizer, static switch,
manual bypass switch, AC/DC distribution boards, other
necessary protective devices and accessories and shall
meet the following requirements as a minimum.
(1) The KVA rating of UPS shall be as required by expected
loads and include 10% spare capacity guaranteed at 50
Deg.C Amb. However, for bidding purpose, a minimum
capacity of 125 KVA shall be considered. If UPS KVA
rating is applicable at a lower ambient temperature than
specified 50 Deg.C, the bidder shall consider Derating
factor of at least 1.5% Deg.C for arriving at the
specified UPS capacity at 50 Deg.C ambient. The UPS
shall have an over load capacity of 125% rated capacity
for 10 minutes and 150% rated capacity for 10 secs. The
inverter shall have sufficient I2t capability to clear
fault in the maximum rated branch circuit. The sizing
of UPS shall be based on the power factor of the loads
being fed subject to a maximum of 0.8.
(2) Each of the redundant chargers & batteries shall meet
the specification requirements as per clause 7.05.00
above.
(3) The UPS system shall be capable of operating without DC
battery in circuit under all conditions of load and the
performance of various components of UPS like inverter,
charger static switch etc. shall be guaranteed without
the battery in circuit.
(4) The UPS system design shall ensure that in case of
failure of mains input power supply to one of the
chargers, the other charger whose mains input power
supply is healthy, shall feed to one or both the
inverters as the case may be as per manufacturer’s
standard practice & continue to charge the DC battery at
all load conditions. The bidder should note that this
situation should not in any way load to the discharge of
the DC battery.
(5) Static Inverters
(i) The static inverter shall be solid state type using
proven pulse width modulation(PWM) quasi square
wave/step wave technique. The inverter equipment shall
include all necessary circuitry and devices to conform
to requirements like voltage regulation, current
limiting, wave shaping, transient recovery, automatic
synchronization etc. The steady state voltage regulation
shall be +/- 1% and transient voltage regulation(on
application/ removal of 100% load)shall be +/-2%. Time
to recover from transient to normal voltage shall not
be more than 50 m sec. Frequency regulation for all
conditions of input supplies, loads and temperature
occurring simultaneously or in any combination shall be
better than +/-0.5%(automatically controlled). The total
harmonic content shall be 5% maximum and content of any
single harmonic shall be 2.5 % maximum. The inverter
efficiency shall be at least 85% on full load and 80% on
50% load. The synchronization limit for maintenance of
synchronization between the inverter and stand by AC
source shall be 48-52 Hz, field adjustable in steps of
0.5 Hz. DC input window of each inverter shall be either
315 – 434 or 320-450 V DC.
(ii) Over load, short circuit and load loss
The inverter shall be provided with suitable HRC fuses
at the input and output which will permit proper
coordination with other protective devices and at the
same time protect the inverter against damage due to
internal faults. However, if the Bidder’s system
design does not use fuses then the fuse free circuit
breaker may also be permitted provided it meets the
specification requirements. All necessary equipment
shall be provided to protect the inverter against over
load, short circuit and 100% loss of load. The inverter
shall be self protecting against damage if energized
with full load connected.
(iii)Inverter equipment shall include all solid state
circuitry and devices including stable oscillator etc. to
enable inverters to operate satisfactorily in parallel
sharing mode each inverter taking 50% load during
normal operation. In case of failure of either
inverter, 100% load shall automatically be transferred
to healthy inverter without any break and degradation in
the quality of UPS output and disconnecting the faulty
inverter automatically.
(iv)The inverter failure shall be alarmed and the healthy
inverter shall get synchronizing signal from the standby
AC source and remain synchronized within the set
limits. The limits for the synchronization between
healthy inverter and standby AC source shall be field
adjustable.
(v) On failure of both inverters, the loads shall be
transferred to standby AC power without a break if
within synchronization limits. Provision of synchronous
transfer with a break in case of inverter being out of
synchronization limits shall also be there with standby
source.
(6) Static Switch and Manual Bypass Switch
The static switch shall be provided to perform the
function of transferring UPS loads automatically without
any break from (i) faulty inverter to standby AC source
in case of failure of both the inverters and (ii)from
faulty inverter to standby AC source in case of failure
of both the inverters.
Manual bypass switch shall be employed for isolating the
UPS during maintenance.
(7) Step Down Transformer and Voltage Stabilizer
The transformer shall be of low impedance type and the
rating shall be such that extremely fast fault clearance
is achieved, even in the largest rated branch circuit.
The winding shall be electrolyte grade copper with F class
insulation with temp rise limited to class B .
The over load capacity of the transformer/ stabilizer
shall not be less than 300% for 200 ms. The stabilizer
shall employ silicon solid state circuitry and the
output voltage regulation shall be +/- 2%. The
efficiency of the stabilizer shall be 95% or better.
7.05.00 (1) Float cum boost chargers:
Bidder shall provide 2×100% redundant chargers. The charge
Shall sized to meet the 100% load requirements of the
control system plus recharge the fully discharged
battery within 8 hours.
The chargers shall be self regulating, solid state
silicon controlled, full-wave rectifier type designed
for single and parallel operation with battery and shall
have automatic voltage regulators for a close voltage
stability even when AC supply voltage and DC load
fluctuates, effective current limiting features and
filters on both input and output to minimize harmonics.
The charger output regulation shall be +/- 1% from no
load to full load with an input power supply variation
of +/- 10% in voltage and +/- 5% in frequency. In
addition to alarms on charger panel, potential free
contacts for alarms like charger O/P voltage high etc.
shall also be provided for use in DDCMIS. Further
isolated 4-20 mA signals shall be provided for important
parameters like charger voltage etc.
(2) Batteries
The batteries shall be heavy duty Lead Acid PLANTE type
and shall be sized for one hours of full load operation.
The PLANTE Lead Acid batteries shall conform to
IS:1652. For all sizing calculation, an aging factor of
0.8 and a temperature correction factor of 0.935(based
on temperature characteristics curve to be submitted by
the contractor and at a temperature of 1 Deg.C).
Capacity factor and end cell voltage 1.85 V after one
hour shall be taken into consideration, if applicable
and ambient temperature shall be considered as the
electrolytic temperature. The battery sizing
calculations shall be as per IEEE-485.
7.06.00 AUXILIARY EQUIPMENTS
All required auxiliary equipment/materials as finalised
during detailed engineering shall be furnished with
each charger/inverter/ battery bank and shall include as
a minimum various meters(AC/DC voltage /current, KVA
power factor, frequency meters etc., circuit breakers,
selector switches, push buttons indicating lights,
ground detector system, battery accessories like inter
cell connectors, inter step connectors, battery racks
etc.)further, isolated 4-20 mA signals for important
parameters and potential free contacts for important
alarms shall be provided for use in DDCMIS.
7.07.00 Bidder shall furnish the power supply distribution
scheme, single line diagram, all calculations such as
charger/inverter rating calculations, battery sizing
calculation etc., during detailed engineering for
MPPGCL’s review and approval.
7.08.00 The winding of transformer shall be electrolyte grade copper
with F class insulation with temp rise limited to class B.
7.09.00 Bidder shall provide following minimum accessories per Battery set for maintenance of battery and safety equipment for maintenance personals.
a) Hydrometer - 5 Nos.
b) Thermometer - 5 Nos.
c) Cell Tester(Voltmeter) - 5 Nos.
d) Alkali Mixing Jar - 5 Nos.
e) Rubber Apron - 5 Nos.
f) Rubber Gloves - 5 Pair
g) Set of Spanners - 5 Pair
h) Spare acid in Container - 25% of Total acid
i) Other accessories as per
Recommendation of Battery manufacturer
j) Specific gravity correction chart - 2 Nos.
7.10.01 U P S (Factory Acceptance Test)
a) Power Efficiency (IEC 146-2, IEC 146)at 100%load,50%load
b) Load Test(Approved Procedure)- Load regulation Test
c) Audible Noise Test (IEC 146-2)
d) Fuse Clearing Capability (Approved Procedure)
e) Relative Harmonic content (IEC-146.2)
f) Synchronous transfer and Synchronization Test (IEC 146-4)
g) Temp. rise test without redundant fans(IEC-146.2)
h) Input voltage Variation Test (Approved Procedure)
i) Over load test on inverter & charger(Approved Procedure)
j) Insulation Test (IEC 146)
k) Restart Test (IEC 146-2)
l) Short Circuit current capability (IEC 146-4- Clause 5.10)
m) Output voltage & frequency tolerance (IEC 146-2)
n) Voltage Current Division (IEC 146-2)
o) Relative Harmonic content (IEC 146-2)
p) Parallel Redundancy Test (* Simulation of parallel redundant
fault (IEC-146.4)
q) Over load Test (Final acceptance Test)
r) Any other required as per National/International standard
or QAP.
7.10.02 Battery Charger
a) Short Circuit current capability (IEC 146-2)
b) Temp. rise test without redundant fans(Approved Procedure)
c) S W C Test (Approved Procedure)
d) Efficiency / PF (IEC 146-2, IEC 146)
e) Audible Noise Test (IEC 146-2)
f) Fuse Clearing Capability (Approved Procedure)
g) Relative Harmonic content (Approved Procedure)
h) Temp. rise test without redundant fans(IEC 146-2)
i) Over load test on charger (Approved Procedure)
j) Restart Test (IEC 146-2)
k) Output voltage tolerance (Approved Procedure)
l) Output Voltage Harmonic content (Approved Procedure)
The above test Clause No.7.10.01 & 7.10.02 shall be witness
By owner / owner’s representative.
7.10.03 Testing at site
Full load test shall be demonstrated after commissioning of
UPS and charger with batteries at site for 72 Hrs.
7.10.04 Type Test
Bidder shall submit following Type Test Report along with
final acceptance report.
a) Battery as per IS – 1652
b) UPS/ Charger
i) IP degree
ii)Surge with stand capability (SWC)
iii)Dry heat Test (IEC – 68.2.2)
iv) Dump heat Test(IEC – 68.2.3)
v) Vibration Test (IEC- 68.2.8)
vi) EMC Test (IEC- 61000.4.2)
The above all Type Test shall be conducted at National/
International Laboratories only.
7.11.05 Bidder shall submit following documents along with factory
acceptance test (FAT) Report –
a) Internal Test Report along with heat run test report.
b) Calibration certificate of measuring instruments.
7.11.06 The contractor shall submit all above test results for
Review and approval.
![Almost Like Another Planet... Pamukkale Blues (UNESCO World Heritage) [Explore #1, THANK YOU] Almost Like Another Planet... Pamukkale Blues (UNESCO World Heritage) [Explore #1, THANK YOU]](http://static.flickr.com/7079/7209710670_f67079c754_t.jpg)
[...] 7.ELECTRIC POWER SUPPLY Leave a Comment [...]
[...] 7.ELECTRIC POWER SUPPLY [...]